Work Breakdown Structure (WBS) Deep Dive
Complete guide to creating and using the WBS for the PMP exam — decomposition rules, 100% rule, and WBS dictionary.
Work Breakdown Structure
The WBS is a hierarchical decomposition of the total scope of work to be carried out by the project team to accomplish the project objectives and create the required deliverables.
Key WBS Rules
- 100% Rule — The WBS must capture 100% of the work defined by the project scope, including project management work
- The lowest level of the WBS is the work package
- Work packages should be decomposed to a level where they can be estimated, scheduled, and monitored
- The WBS is deliverable-oriented, not activity-oriented
- The WBS defines scope — if it's not in the WBS, it's not in the project
WBS Components
- Level 1 — Project name
- Level 2 — Major deliverables or phases
- Level 3+ — Sub-deliverables, broken down further
- Work Package — Lowest level, the basis for estimating and managing
WBS Dictionary
A companion document that provides detailed information for each WBS element:
- Description of work
- Responsible organization
- Schedule milestones
- Quality requirements
- Cost estimates
- Acceptance criteria
- Technical references