Earned Value Management (EVM) Cheat Sheet

Quick reference for all PMP EVM formulas, interpretation rules, and worked examples.

Earned Value Management — Quick Reference

Core Variables

TermDefinitionFormula
PV (Planned Value)Budgeted cost of work scheduledFrom baseline
EV (Earned Value)Budgeted cost of work performed% Complete × BAC
AC (Actual Cost)Actual cost of work performedFrom accounting
BAC (Budget at Completion)Total planned budgetFrom baseline

Variance Formulas

FormulaMeaningGoodBad
CV = EV − ACCost variancePositive (under budget)Negative (over budget)
SV = EV − PVSchedule variancePositive (ahead)Negative (behind)

Performance Indices

FormulaMeaningGoodBad
CPI = EV / ACCost efficiency> 1.0< 1.0
SPI = EV / PVSchedule efficiency> 1.0< 1.0

Forecasting

FormulaWhen to Use
EAC = BAC / CPIPast performance will continue (most common)
EAC = AC + (BAC − EV)Past variance was atypical (won't continue)
EAC = AC + [(BAC − EV) / (CPI × SPI)]Both cost and schedule affect remaining work
ETC = EAC − ACEstimate to complete from now
VAC = BAC − EACVariance at completion
TCPI = (BAC − EV) / (BAC − AC)Required future CPI to meet BAC

Memory Trick

EV always comes first in subtraction formulas (CV = EV−AC, SV = EV−PV) and in the numerator of index formulas (CPI = EV/AC, SPI = EV/PV).

Negative variance = bad. Index < 1.0 = bad.

Ready to start practicing?

Join thousands of PMP candidates using PMPprep to pass their exam.

Start Studying Free