Earned Value Management (EVM) Cheat Sheet
Quick reference for all PMP EVM formulas, interpretation rules, and worked examples.
Earned Value Management — Quick Reference
Core Variables
| Term | Definition | Formula |
|---|---|---|
| PV (Planned Value) | Budgeted cost of work scheduled | From baseline |
| EV (Earned Value) | Budgeted cost of work performed | % Complete × BAC |
| AC (Actual Cost) | Actual cost of work performed | From accounting |
| BAC (Budget at Completion) | Total planned budget | From baseline |
Variance Formulas
| Formula | Meaning | Good | Bad |
|---|---|---|---|
| CV = EV − AC | Cost variance | Positive (under budget) | Negative (over budget) |
| SV = EV − PV | Schedule variance | Positive (ahead) | Negative (behind) |
Performance Indices
| Formula | Meaning | Good | Bad |
|---|---|---|---|
| CPI = EV / AC | Cost efficiency | > 1.0 | < 1.0 |
| SPI = EV / PV | Schedule efficiency | > 1.0 | < 1.0 |
Forecasting
| Formula | When to Use |
|---|---|
| EAC = BAC / CPI | Past performance will continue (most common) |
| EAC = AC + (BAC − EV) | Past variance was atypical (won't continue) |
| EAC = AC + [(BAC − EV) / (CPI × SPI)] | Both cost and schedule affect remaining work |
| ETC = EAC − AC | Estimate to complete from now |
| VAC = BAC − EAC | Variance at completion |
| TCPI = (BAC − EV) / (BAC − AC) | Required future CPI to meet BAC |
Memory Trick
EV always comes first in subtraction formulas (CV = EV−AC, SV = EV−PV) and in the numerator of index formulas (CPI = EV/AC, SPI = EV/PV).
Negative variance = bad. Index < 1.0 = bad.
Ready to start practicing?
Join thousands of PMP candidates using PMPprep to pass their exam.
Start Studying Free